EirGrid

3 June 2026

EirGrid RMS model specification Data Centre_V1.0 (June 2026)

This document has been published by the TSO to provide clarity on the balanced root mean-square positive phase-sequence (RMS) modelling requirements for Data Centres in Ireland, as specified in the Grid Code (PC.A8) [1.], in compliance with European legislation EU 2016/1388 reflected in the Network Code on
Demand Connection (Article 21) [2.]. The contents of this document are also in alignment with the recommended amendments to the existing Network Codes submitted by ACER to the European Commission in December 2023 (DCC 2.0) [3.], expected to be approved in 2026.