NIE and ESB National Grid Louth - Tandragee 275kV Feasibility Study ( South of Border ) ESBI Report No. PE687-R141-002-001-001.doc

A Joint ESB National Grid (ESB) / Northern Ireland Electricity (NIE) steering
committee requested that a feasibility study of potential 275kV Interconnection be
carried out in February 2003. This report assessed the feasibility of a new 275kV
line between Arva 110kV station and Drumkee 275kV Station.