20 February 2004
NIE and ESB National Grid Arva - Drumkee 275kV Feasibility Study ESBI Report No. PE687-R102-001-001-000.doc
This report recommended that if a transmission line connection is required between Arva
and Drumkee 275kV station, that further detailed route assessment be undertaken based
upon the potential route corridors as detailed in this report It is recommended the line
(whether single or double circuit) should be constructed using standard lattice steel
towers. The report finally concluded that an overhead line route corridor exists between
Arva to Drumkee.